TME Conducts Training for Caltrans Engineers

TME Projects

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

TME Conducts Training for Caltrans Engineers

February 20, 2013. TME is partnering with URS Corp to conduct a series of statewide training courses for Caltrans. Each two-day course begins with an overview of water pollution control requirements and responsibilities, and ends with a hands-on field demonstration.

The field demo allows Resident Engineers and other Caltrans staff to see first-hand how BMPs such as hydro-mulch, DI protection, fiber rolls, silt fence, and check dams are properly implemented. Participants get to try their hand at straw mulching and hydro-seeding, among other activities.

TME’s reputation as California’s foremost Storm Water authority was key in its selection for the job. The courses, which are part of Caltrans’ Resident Engineer Certificate Program, will be taking place throughout the months of January, February, and March 2013.

Gallery

Peterson Ranch Advanced Storm Water Treatment System

TME Projects

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Peterson Ranch Advanced Storm Water Treatment System

Peterson Ranch in Suisun, CA is a housing development recently built out by K Hovnanian Homes. The site discharges to a wetland to the south that eventually runs into Suisun Bay. Fairfield Suisun has stricter guidelines due to the Suisun Bay water quality concerns.

The site is relatively flat but the soils are very fine colloidal clays. Thunder Mountain designed this advanced treatment system to protect the wetland that flows to Suisun Bay during wet season construction, resulting in a clean outflow less than 10 NTU.

Gallery

Sacramento Residence Rainwater Harvesting System

TME Projects

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Sacramento Residence Rainwater Harvesting System

A residential rain water harvesting system was placed under a large patio in back yard.  Thunder Mountain designed the retention tank, which can be used for irrigation and emergency water source in case of fire. The retention tank, when full, overflows into a secondary detention tank where the water can infiltrate and recharge the water table. Rainwater enters the tank through pervious pavers and filtered water from roof downspouts. The tanks can collect and infiltrate as much as 60,000 gallons of rain water per year.

Gallery

Highway 126 Drainage Improvements (Caltrans)

TME Projects

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Highway 126 Drainage Improvements (Caltrans)

Highway 126 Drainage Improvements
Project Owner: Caltrans
Project Location: Napa County, California

Installation of 3 drainage systems across Highway 126 near Napa.  Thunder Mountain removed and replaced two 18” culverts, added downdrains and installed underdrain system to prevent further road deterioration from undermining from water seeping from the uphill bank underneath the road.

Gallery

Folsom Bridge

TME Projects

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

Folsom Bridge

As an integral component of The Central Valley project, the Folsom Dam was built in 1955 by the U.S. Corps of Army Engineers roughly twenty-three miles northeast of the City of Sacramento.  It is currently operated by the U.S. Bureau of Reclamation.  Located right below Folsom Dam is the Folsom Power Plant, which produces approximately 198,207 kilowatts of electricity (equivalent to 10% of the power consumed by the City of Sacramento) through the use of three turbines.  These turbines generate electricity by harnessing controlled gravitational releases of water from Lake Natoma.  These releases eventually run into the American River which flows to the Sacramento River, and is subsequently expelled into the San Francisco Bay.

Thursday, February 22nd 2007 marked the ground breaking ceremony for construction of the Folsom Bridge Project.  After the September 11th attacks on the World Trade Center buildings, a comprehensive review of sites that had potential to be terrorist targets was conducted by U.S. Bureau of Reclamation.  Due to the proximity and population density surrounding the Folsom Dam, it was determined that continued public access to the Folsom Bridge Road posed too great a risk.  As a vital artery for transportation across the city of Folsom, its closure would put undo stress on the remainder of the city’s thoroughfares, thus an alternative route had to be constructed.

The Folsom Bridge construction site is a joint venture between U.S. Army Corps of Engineers, U.S. Bureau of Reclamation and the City of Folsom.  The site itself occupies 380 acres, 80 acres were to be disturbed to construct the Roadway and Bridge.  The New Folsom Bridge was to be constructed over  the pristine American River that runs crystal clean most of the year.  During the first wet season significant changes were required to the initial design of the Storm Water Pollution Prevention Plan including shed-on calculations, site topography and soil characteristics.  Several slope failures, inadequate basin sizing and two notices of violation from the Regional Water Quality Control Board expedited the reevaluation of the SWPPP.  After these failures were identified, the City of Folsom hired Beth Smiley of Thunder Mountain Enterprises as an outside consultant for the purposes of assisting in SWPPP design update, site monitoring and help keep the site out of trouble with the State.

Thunder Mountain Enterprises worked in collaboration with City of Folsom, US Army Corps of Engineers and the prime contractor to address SWPPP design deficiencies.  The sheds were evaluated and diversions and pumping was implemented.  The slope stabilization for temporary erosion control was redesigned.  The contractor and original SWPPP design consultant assumed the permenant erosion control would be sufficient for the slopes and soil type.  Some critical areas were redesigned with Profile Products Green Armor System.  It was soon discovered that the premise behind the original Storm Water Pollution Prevention Plan was contingent upon the assumption that the decomposed granite, a major constituent of the soil on-site, would allow rapid infiltration of storm water.  When storm water did not infiltrate due to steep topography, abundance of rock granite formations below the surface and significant shed-on the rainfall that occurred on the site created massive amounts of watershed .by increasing erosive forces on unstabilized soil.  As the on-site hydrology failed to infiltrate and began to move, the topography of the project became an important factor to consider.  Cuts made through the hills adjacent to the Folsom Dam to facilitate road access to the Folsom Bridge, resulted in very steep (1:1, 2:1) slopes with very long runs (some in excess of 50 linear feet).  In most cases these very long running, steep slopes served to amplify erosion by increasing the sheer strength of storm water on already highly erodible soils.  To further complicate matters, the calculation of actual acreage that would shed storm water on to the project site was grossly underestimated.  All of these factors combined contributed to numerous instances of erosion, slope failure, pooling and turbid water discharge.

After the aforementioned problems were identified, Thunder Mountain began putting together a plan to address each of these particular concerns.  Beth Smiley was responsible for completely redesigning the existing slope protection in an effort to re-stabilize areas that had already failed, and ensure continued stability for the duration of the project.  This goal was achieved with the use of Profile Products’ Green Armor System for permanent slope stabilization around critical locations, and their general Erosion Control system for temporary erosion control.  The use of both temporary and permanent erosion control systems was necessary to satisfy multiple challenges that the Folsom Bridge Project involved.

Profile Products’ Green Armor System was developed as an alternative to what is known as “Hard Armor,” which mainly involves the use of stone or rock in storm water management.  Advantages to using the Green Armor System over a hard armor design abound.

Gallery

12 Bridges, Village 9

TME Projects

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

12 Bridges, Village 9

Twelve Bridges, Village 9, owned by Placer Holding, Inc. infrastructure was constructed the winter of 2006 in the rolling hills of Lincoln, CA. The soils are very fine and tricky when constructing during wet season. The Storm Water Pollution Prevention Plan was prepared by Beth Smiley, CPESC, CPSWQ of Thunder Mountain Enterprises, Inc. The soils, hydrology, including 100 acres shed-on to the site, construction timeline and adjacent creek as receiving waters were significant considerations in the design. Advanced Treatment of Storm Water was considered highly likely early on due to the fine clayey soils, three outfalls directly into the creek and a construction timeline that would certainly get into wet season grading and underground utilities.

The 133 acre site had multiple other challenges. Experienced Construction Management of Rob Parish from Parish and Associates in this region emphasized proactive Storm Water Pollution Prevention Plan preparation. Among the many challenges were multiple outfalls into the creek that were designed to be vegetated instead or hard armor with the influence of Thunder Mountain. There were massive cuts and fills and many terraced lots. The slopes of the lots were seeded and blanketed due to the sensative nature of the soils. There is an open space to the east with many slopes that were also seeded and blanketed and silt fenced for protection until vegetative establishment.

The mild early winter allowed half of the site to pave prior to significant rainfall. So, the Advanced Treatment System could be downsized to treat less storm water discharge. However, the inability to dig a basin required multiple tanks to capture the rain event, be treated in secondary tanks, run through sand filtration before being discharged at below 10 NTU. The site treated millions of gallons.

Gallery